问题 桥梁深水基础钢板桩围堰的施工顺序是( )。
选项 A.定位桩插打→围囹安装→钢板桩插打→钢板桩合龙 B.围囹安装→定位桩插打→钢板桩插打→钢板桩合龙 C.钢板桩插打→定位桩插打→围囹安装→钢板桩合龙 D.钢板桩插打→围囹安装→定位桩插打→钢板桩合龙
答案 A
解析

相关内容:桥梁,深水,基础,钢板,围堰,施工,顺序,定位,桩插,围囹

猜你喜欢

发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.