在正常施工条件下,完成10m3混凝土梁浇捣需4个基本用工,0.5个辅助用工,0.3个超运距用工,若人工幅度差系数为10%,则该梁混凝土浇捣预算定额人工消耗...

作者: rantiku 人气: - 评论: 0
问题 在正常施工条件下,完成10m3混凝土梁浇捣需4个基本用工,0.5个辅助用工,0.3个超运距用工,若人工幅度差系数为10%,则该梁混凝土浇捣预算定额人工消耗量为(  )工日/10m3。
选项 A、5.20 B、5.23 C、5.25 D、5.28
答案 D
解析 预算定额人工消耗量=(4+0.3+0.5)*(1+10%)=5.28(工日/m3)
发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.