电梯井道放基准线后的工序是()。A、安装导轨 B、配管配线 C、轿厢组装 D、电机安装

作者: rantiku 人气: - 评论: 0
问题 电梯井道放基准线后的工序是()。
选项 A、安装导轨 B、配管配线 C、轿厢组装 D、电机安装
答案 A
解析

猜你喜欢

发表评论
更多 网友评论0 条评论)
暂无评论
错误啦!

错误信息

  • 消息: [程序异常] : MISCONF Redis is configured to save RDB snapshots, but it's currently unable to persist to disk. Commands that may modify the data set are disabled, because this instance is configured to report errors during writes if RDB snapshotting fails (stop-writes-on-bgsave-error option). Please check the Redis logs for details about the RDB error.